To complete a task in 16 days a company needs
5 people each working for 6 hours per day.
The company decides to have
8 people each working for 4 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?

Respuesta :

Otras preguntas

Does everyone do their homework late Sunday night?
Lloyd has $20,000 to deposit. His wife’s illness leads to medical expenses beyond what their insurance will cover, so Lloyd must often quickly access his saving
How do you write 304,800,400 in expanded form
They wait. → Ellos a0.
If you suspect someone you know may attempt suicide, you should __________.
Between what two numbers would 9 be located on a number line? A. 10 and 11 B. 9 and 10 C. 7 and 8 D. 8 and 10
What does it mean to estimate?
sentence for compressions
a mail truck travels 82 miles in 412 hours. to the nearest tenth, what was the average speed of the mail truck? enter your answer in the box.
Daniel left a $9 tip for the waiter at a restaurant. If the tip was 15 percent of the bill, how much was the bill?