X can do a piece of work in 20 days, y in 15 days. x and y work at it together for 8 days and then z finishes it in 4 days. how much time it would take to do it alone?

Respuesta :

Otras preguntas

Can someone help me out please ?
upply and demand Question 8 of 10 Which situation would cause the price of a product to fall the most? A. Both the demand and the supply fall. B. Both the deman
PLEASE HELP!!!!! All my points Picture below
I need help I am timed please 1/4c+5/3c-4=2-1/12 What dose c equalu
Joan typed an entire page of her English essay. She is now at the bottom of her document and can’t see the top. What should Joan use to see the top of the docum
What was a result of Napoleon’s economic reforms in France? Taxes were based on fixed rates and were no longer a surprise. The lower classes were no longer req
What region of the United States is characterized by mountains, rivers, lakes, and Atlantic coast line?
mutations! 1. Mutations are changes in DNA which can sometimes change the DNA I 2. Mutations can be or be caused by exposure to harmful or Anything in the envir
what is the image of (-2, -5) after a reflection over the line y = x
To solve the logarithmic inequality below, Braden decides to first create a table of values representing the left side of the inequality. Which statements accur