(1) Draw a network diagram for the project given below: (1) A is the first operation of the project. (2) B and C can be done concurrently and both must follow A. (3) B must precede D. (4) E cannot begin until C is completed. (5) F is dependent on the completion of both D and E. (6) F is the last operation of the project.