a 950 N skydiver jumps from an altitude of 3000 m. What is the total work performed on the skydiver?

Respuesta :

quasarJose
quasarJose quasarJose
  • 16-01-2021

Answer:

2850000J

Explanation:

Given parameters:

Weight of diver = 950N

Altitude  = 3000N

Unknown:

Total work done by the sky diver = ?

Solution:

To solve this problem, we use the expression:

        Work done  = Weight x height

Now insert the parameters:

        Work done  = 950 x 3000  = 2850000J

Answer Link

Otras preguntas

Solve and check 7/8h-5/8=2
Why is the equation incorrect? Mg₃ + N₂ → Mg₃N₂ (A) Some of the subscripts are incorrectly used. (B) The equation is not balanced. (C) The valence of the n
A 15 cm3 block of gold weighs 2.8 N. It is carefully submerged in a tank of mercury. One cm3 of mercury weighs 0.13 N. a. Will the mercury be displaced by the g
Describe Columbus crew
How do I solve 5 1/2 divided by -2 3/4
Solve 7x-6 > 8 and 3x + 4> 22 for x. Could you please help solve this.
What was Mr.Bach's "Fight for freedom"?
if the measure of angle one is "two-x minus nine" and the measure of angle two is "twenty seven minus four-x", solve for x.
which sentence shows correct subject- verb agreement? A. My friend and her mother were listening to the radio. B. My friend and her mother was listening to the
The equation x2 + y2 − 2x + 2y − 1 = 0 is the general form of the equation of a circle. What is the standard form of the equation?