4) The overall project budget is $20,000. At Week 8, the actual cost is $9,000 and the CPI is

1.1. What is the earned value of the project at Week 8?

Respuesta :

andromache andromache
  • 17-02-2021

Answer:

the earned value of the project is $9,900

Step-by-step explanation:

The computation of the earned value of the project is shown below:

As we know that

CPI = Earned value ÷ Actual cost

1.1 =  Earned value ÷ $9,000

So, the earned value is

= 1.1 × $9,000

= $9,900

hence, the earned value of the project is $9,900

Answer Link

Otras preguntas

What is the average of the integers from 25 to 41? 27, 33, 36, 66 ?
The sum of the digits of a two-digit number is 9. If the digits are reversed, the new number is 27 less than the original. Find the original number.
x^2 + 3x - 18 = 0 Solve using the quadratic formula
the volumes of two spheres are 729 in3 and 27 in3. what is the ratio of their radii, rounded to the nearest whole number?
to meet building codes, a building must have a roof no taller than 96 feet.an architect is designing an office building with an 18 3/4 foot ground floor, and 11
The formula for the height of a ball as a function of time is given by the equation h = -16t^2 + vt + h, where h is the height of a ball in feet, v is the initi
which fraction is larger 1/3, 2/5, 8/15, 13/30. and how do i solve this
Write the equation of the line passing through the given point with the indicated slope. Give your results in slope-intercept form. Point : (0,5) Slope: m=-3/
What is the reference angle for -275 degrees?
Estimate the answer by first rounding each value,then performing the operation