Three men working together can finish a house repair job in 10 days. How manydays will 5 men working at the same rate finish the same job? *

Respuesta :

berno berno
  • 12-04-2021

Answer:

17 days

Step-by-step explanation:

Number of days in which 3 men can finish a house repair job = 10 days

Number of days in which 1 man can finish a house repair job = [tex]\frac{10}{3}[/tex] days

Therefore,

Number of days in which 5 men can finish a house repair job = Number of days in which 1 man can finish a house repair job × 5

[tex]=\frac{10}{3}(5)=\frac{50}{3}=16.6[/tex] ≈ 17 days

Answer Link

Otras preguntas

FIND THE ERROR AND CORRECT:Don't worry about her; she just feels like to stay home alone tonight
Dolley Madison wrote a letter to her sister describing: her escape from the White House during the War of 1812. the lynching of an African American man in the s
What time is shown on the clock?
After the game, the team danced in a huddle. Select one: t of a. phrase b. independent clause c. subordinate clause
If y varies inversely as x and y= 2/5 when x= 2, find y when x= 1 equation
38 is 95% is what number?
Anyone like anime like Bungou stray dogs (I'm still reading the manga so no spoilers), Ouran host high school club, MHA, Moriarty the patriot (SherLiam ️) and m
Which of the following shows a negative stance on afterschool sports
help find x for a,b,c and d i will rate thank u
If f(x) = + 8, what is f(x) when x = 10? O4 O 9 O 13 O 36