Leah can build a brick wall in 7 hours, while her apprentice can do the job in 10 hours. How long does it take for them to build a wall together

Respuesta :

masterdestroyer27
masterdestroyer27 masterdestroyer27
  • 12-11-2021

Answer:

70/17 hours or 4 2/17 hours

Step-by-step explanation:

The equation we use is 1/7 + 1/10 = 1/x, x being the time it took them together to build. x works out to 70/17 hours

Answer Link

Otras preguntas

A baseball is thrown upward with an initial velocity of 88 feet per second (Vo = 88). When will the ball be 120 feet above the ground? [h(t) = -16t2 + vot].
PLZZZZZZZZZ HELPPPPPPPPPPPPP
can yall pls help, i need help
Can somebody answer this
1. Solve each problem and check your answer using estimates. a. $18.79 + $2.11 + ‐$1.92 + $17.28 b. $7.45 + ‐$24.45 + $74.17 + ‐$76.52 c. $98.45 − $10.63 + $2.8
The function of number 1 in the picture below is to –
Question 7 of 10 Evaluate the expression and enter your answer below. V64 v4
How do muscles help the body move?
PLEASE HELP! I am having trouble answering the last question.
what a meaning this ;)