It took 6 people to paint several offices in 5 days. how many more people need to be hired to complete the same job in 3 days

Respuesta :

Davidfridman
Davidfridman Davidfridman
  • 12-01-2018
it would be 4 more people
Answer Link
eudora eudora
  • 15-10-2019

Answer:

4 more people

Step-by-step explanation:

6 people can paint several offices in 5 days

1 people can do same work in = 6 × 5 = 30 days

To complete the same job in 3 days people need = [tex]\frac{30}{3}[/tex]

                                                                = 10 people

Need to hire people = 10 - 6 = 4 people

4 more people need to be hired to complete the same job in 3 days.

Answer Link

Otras preguntas

can someone help me plz
The Internet has lowered the entry barriers for smaller firms that wish to diversify into international markets. Why is this so
What is the correct meaning of the word method? My brother came up with an unusual method for cleaning his room. (a way of doing something (a new idea (a useful
What is 2+2 Im stuck on the question help me asap.
why was germany able to defeat france so quickly in world war 2
Which graph represents y=x−2
What is the slope intercept form of the linear equation x + y = 12
(Solve for r) 56 = 7r Also explain how you got it.
simplify the equation ​
Flounder Corporation owns machinery that cost $26,400 when purchased on July 1, 2017. Depreciation has been recorded at a rate of $3,168 per year, resulting in