One-half of a road construction project was completed by 6 workers in 12 days. working at the same rate, what is the smallest number of workers needed to finish the rest of the project in exactly four days?

Respuesta :

mkryukova19 mkryukova19
  • 14-04-2018
6 workers*12 days=x workers*4 days
x=6*12/4=3*6=18 workers are needed
Answer Link

Otras preguntas

Please help ASAP!!!!!!!!!
Please help and explain how too simplify a radical equation
Choose the statement from the following choices that best describes the separation of powers. A. Powers and duties of the United States government are d
1. Which does not accurately describe the Cuban missile crisis? A. United States announced the blockade of Cuba B. The Soviet Union and the United States were o
What do we need to do?
PLEAS HELP ASAP!! What are all living things made of? At least one cell At least one tissue with many cells Several organs Several organ systems with many o
what is "are my" in spanish
by comparing medians which person went to the movies the most per monthalso tell me how you did it i would appreciate it alot ​
Help asap 10 points
Which of these statements is correct